Pembangunan Saluran Air di Jl Kikir Kayu Putih Capai 25 Persen

Channel Development on Jalan Kikir Kayu Putih Reaches 25 Percent

It is targeted to be completed in the next two and a half months

The water channel development up to 1,178 meters on Jalan Kikir, Kayu Putih Urban Village, Pulogadung, East Jakarta, which has been ongoing since early August 2021 has touched 25 percent.

Drainage Development and Improvement Division Head, Tengku Saugi Zikri said, it was aimed at following up on residents' requests submitted through the Musrenbang.

East Jakarta Develops Drainages in Seven Locations

During the 2020 Musrenbang, they proposed the development of a water channel in order to anticipate flooding in the rainy season. Most channels were damaged, moreover some points should be built new channels.

"It is targeted to be completed in the next two and a half months," he uttered, Tuesday (8/24).

He added, it would spend a budget of Rp 2,029 billion. Its development was done through e-catalog purchasing system.

"Hopefully, it is able to minimize flooding when it rains. This water channel material uses U-Ditch concrete with a size of 60 centimeters," he concluded.

Linked News
Popular News indeks
  1. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1155 personFolmer
  2. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1044 personNurito
  3. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye978 personFolmer
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye926 personDessy Suciati
  5. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye771 personAldi Geri Lumban Tobing